Mining · Ethiopia

Kurmuk Gold Mine Potable Water

Published case study references a 33-day installation, 159 kW/day energy use and continuous monitoring.

Published project proof point33 days

published installation period

Published SewTreat project record
LocationKurmuk, Ethiopia
Capacity400 KLPD potable water treatment plant
ApplicationMining
Treated-water destinationPotable water for camp, plant and services

Visual project record

See the treatment context, not only the claims.

Named-project photographs are identified as project images. Supporting photographs are labelled as representative SewTreat system references.

Alternative-source treatmentSystem reference

Alternative-source treatment

Representative borehole-water treatment and storage configuration.

Clarification and solids removalProcess reference

Clarification and solids removal

Representative clarification stage selected around the verified raw-water profile.

Membrane polishingProcess reference

Membrane polishing

Representative ultrafiltration equipment and final polishing context.

Executive project brief

The challenge

Raw borehole and dam water exceeded the referenced drinking-water standard, with high turbidity, total suspended solids and alkalinity creating disinfection and worker-health risks.

Hydraulic duty400 KLPD potable water treatment plant
Water streamWater
Operating contextMining
Required destinationPotable water for camp, plant and services

Solution architecture

The following elements are documented in SewTreat’s published project record.

  1. Large-scale containerised water treatment plant
  2. Solids removal, clarification and final disinfection
  3. Automated continuous monitoring
  4. Remote-site transport and installation strategy
  5. On-site supervision and commissioning

Engineering assurance

Characterise

Validate the water profile, duty and variability.

Integrate

Define civils, power, controls, storage and existing interfaces.

Operate

Plan access, skills, residuals, consumables and maintenance.

Verify

Agree commissioning, sampling and acceptance evidence.

Published outcome

Published case study references a 33-day installation, 159 kW/day energy use and continuous monitoring.

What the project demonstrates

  • Potable-water security
  • Remote deployment
  • Automated performance monitoring
  • Scalable mine support

Before procurement

  1. Representative water analysis completed
  2. Average, peak and future flows validated
  3. Required standard and destination made explicit
  4. Civils, utilities, storage and distribution interfaces defined
  5. Operating and maintenance model resourced
  6. Commissioning evidence and acceptance criteria agreed

Source: Kurmuk Case Study. Financial and performance figures are attributed to SewTreat’s published case-study material.

Published project evidence

The original SewTreat case-study record.

The complete source sheet is shown alongside the web case study so the project photography, published figures and treatment narrative remain inspectable.

Open the case-study PDFSource: Kurmuk Case Study
Kurmuk Gold Mine Potable Water published case-study sheet 1
Published case-study sheet 1 of 2
Kurmuk Gold Mine Potable Water published case-study sheet 2
Published case-study sheet 2 of 2

Engineer-led next step

Discuss a similar water or wastewater project.

Share the source, flow and outcome you need. Water Treat can use that context to prepare a useful first technical conversation.

Request a Water Audit No-obligation technical enquiry