Executive project brief
The challenge
Unreliable council supply and borehole water containing turbidity, iron and manganese created a need for an independent treated-water supply.
Solution architecture
The following elements are documented in SewTreat’s published project record.
- 37 KL raw-water storage
- Containerised AFM, GAC and DMI filtration
- Bag filtration and chlorine disinfection
- 72 KL clean-water storage
- Automated dosing, monitoring and municipal switchover
Engineering assurance
Characterise
Validate the water profile, duty and variability.
Integrate
Define civils, power, controls, storage and existing interfaces.
Operate
Plan access, skills, residuals, consumables and maintenance.
Verify
Agree commissioning, sampling and acceptance evidence.
Published outcome
Published case-study claim: over R1.2 million annual saving and 1.2-year payback.
What the project demonstrates
- 67 m3/day treated-water supply
- Reduced council dependence
- Automated operation
- Published saving and payback claim
Before procurement
- Representative water analysis completed
- Average, peak and future flows validated
- Required standard and destination made explicit
- Civils, utilities, storage and distribution interfaces defined
- Operating and maintenance model resourced
- Commissioning evidence and acceptance criteria agreed
Source: Carletonville Case Study. Financial and performance figures are attributed to SewTreat’s published case-study material.